All Projects

Cote Gold Mine Camp Dismantles

Project Location

Janvier, AB

Project Date

Q1 – Q2 2024

Project Scope
  • Current Project Completion: 30%
  • Current Project TRIF Rating: 0.00
  • Camp Size:
    • Chester Camp:
      • Seven (7) – 44-Bed Skidded Dorms
      • 9-Unit Kitchen/Diner Facility
      • 5-Unit Recreation Facility
      • 3-Unit Administration Office
    • Expansion Camp #1:
      • Five (5) – 44-Bed Skidded Dorms
    • Expansion Camp #2:
      • Six (6) – 44-Bed Skidded Dorms
Project Description
  • The removal of the two dorms occurred near Janvier, AB, taken from a decommissioned camp, including the individual shrink wrapping of each module prior to shipment by our Client across the country.
  • Receiving and reinstallation of the dorms on piles at the Musselwhite mine site, located north of Pickle Lake, ON. In addition to installing these dorms, Karve was contracted to complete Client requested retrofits, connect these new dorms to the existing dorms and kitchen via boot rooms and arctic corridors, and expand the existing kitchen diner complex by installing four new modules.